Ticona GmbH
End customer
Ticona GmbH Frankfurt
Parent company
Celanese Corporation USA
Location
Frankfurt-Hoechst Industrial Park
Project name
Ticona TIGer Project
General Project Description
Due to the expansion of Frankfurt Airport, the Ticona plant located in Kelsterbach will move to Frankfurt-Hoechst by 2011.
Project scope
- Task: Planning, delivery, commissioning and instruction
- System: General alarm, public address and communication systems
- Scope of delivery/details:
- 6 INTRON-D plus systems
- Approx. 100 call stations
- Approx. 1000 loudspeakers
- 17,000 W of amplifier output
- Schedule: Planning completed in 2009, delivery and partial commissioning starting 2010, completion in 2011
- Parties involved in the project:
- General contractor: Flour
- Planning: Hochtief
- Construction and Installation: Zoth
Special features
- General alarm, public address and communication for the entire production facility, the 6 INTRON-D plus systems are linked together using a ring structure
- Interfaces to fire- and nitrogen alarm systems
- Control room with six master call stations including headset. Dynamic activation and deactivation of various operation areas.
- Call connections to the different individual systems with talk-back function
- Error message monitoring with interface to the process control system
- Implementation of all systems according to the EN 60849 / VDE 0828 / VDE 0833 standards for electro-acoustic emergency systems